For more photos of the VIP Tour and this week's course photos, click here: July 18th, Photos
On the construction end of things, the team had another very productive week. Highlights include:
1) Hole #1 was seeded (4 holes left to go!)
2) Drainage and irrigation was installed in the chipping/pitching green
3) Sand mix was added to the Putting Green, Hole #9 & Hole #10
4) Prep work will be completed on Hole #11 by Tuesday for seeding
5) Bridge construction to the tees on #12 began
They remain very optimistic that by the end of next week they will have both #11 and #9 seeded, leaving only #10 and #18 to complete. On the grow in side, Tracy added #3 and #8 greens to his mowing rotation this week bringing the total to 10 greens and 5 fairways that are being mowed.
J3 Engineering submitted our second round of civil drawings for the Starter Clubhouse to the City of Aurora this week, and Eidos is putting the final touches on the constructions drawings scheduled to be submitted next week.
Other than that, all I can say is that each day I can see more and more green out my window! Have a Great Weekend!